Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 19, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Amount of $102,870.00 Credit and a Time Extension of 30 Calendar Days, and Acceptance of Project for Softball Field Lighting at
King High School

EXECUTIVE SUMMARY

RHC and Associates, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On August 21, 2007, the Board awarded the contract to M. Gay Constructors, Inc., the low bidder. The scope of work provided for demolition and replacement of the softball field lighting system at King High School.

Change Order No. 1 provides for direct purchase of material and a 30 calendar day time extension for changes to the incoming power.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: 2 Mill

Contract Status:
Contract Sum: $179,000.00
Change Order No. 1 Recommended Herein: $102,870.00 Credit
Revised Contract Sum: $76,130.00
Payments to Date: $75,210.00
Balance Due: $920.00
Contract Completion Date: December 29, 2007
30 Calendar Day Time Extension: Recommended Herein
Revised Completion Date: January 29, 2008
Substantial Completion Date: January 29, 2008

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.12
Hillsborough County Public Schools (Florida) * Mtg.#20090519_351 * Section A Item# 6.12