Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 19, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 5 in the Credit Amount of $30,034.45 and Acceptance of Project for Classrooms for Kids Addition at
Valrico Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Carruthers & Associates Architects P.A. and Manhattan Construction Company to provide design and construction management services. The scope of work provides for an additional 16 classrooms. This addition is necessary to meet class size reduction requirements.

This change order provides for return of unused contingency funds.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,812,695.00
Change Orders Previously Approved: $413,126.37 Credit
Change Order Recommended Herein: $30,034.45 Credit
Revised Guaranteed Maximum Price: $2,369,534.18
Payments to Date: $2,368,534.89
Balance Due: $999.29
Revised Construction Cost: $2,841,706.23

Contract Completion Date: August 4, 2008
Substantial Completion Date: August 5, 2008

EVALUATION

SUBMITTED BY: Eugene Runnels

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004