Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 9, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Amount of $189,112.00 Extra and a Time Extension of 28 Calendar Days and Change Order No. 2 in the Amount of $80,859.00 Extra and a Time Extension of 42 Calendar Days for Roofing Repairs at
Hillsborough High School

EXECUTIVE SUMMARY

Walbridge Aldinger Company was selected from the approved Continuing Services Consultants list to provide construction management services. The scope of work provides for roof repairs at Hillsborough High School.

Change Order No. 1 provides for repairs to roof framing required due to unforeseen and extensive water and termite damage uncovered during the repairs. The change order includes additional gutters and modifications to the slate roof support system recommended by the architect to prevent future deterioration. A time extension of 28 calendar days is included for completion of this work.

Change Order No. 2 provides for repairs to the roof and walls damaged during termite treatment of the building. The pest control company’s insurance provider will pay the cost of this repair. A time extension of 42 calendar days is included for completion of this work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

Funds for Change Order No. 1 are included in the District Capital Outlay: Local Millage. Change Order No. 2 will be paid from insurance proceeds.

Contract Status
Contract Sum: $321,897.00
Change Order No. 1 Recommended Herein: $189,112.00 Extra
Change Order No. 2 Recommended Herein: $80,859.00 Extra
Revised Contract Sum: $591,868.00
Revised Construction Cost: $591,868.00

Original Completion Date: April 10, 2009
Time Extensions Recommended Herein: 70 Calendar Days
Revised Completion Date: June 19, 2009

EVALUATION

SUBMITTED BY: Clay Ward, Manager, Facilities Maintenance Support

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.23
Hillsborough County Public Schools (Florida) * Mtg.#20090609_352 * Section A Item# 6.23