Facilities Action Item |
DATE: Tuesday, July 14, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On May 20, 2008, the Board appointed the architectural firm of Woodroffe Corporation Architects to provide design services. On July 15, 2008, the Board appointed the construction management firm of Batson-Cook Company. The scope of work provides for an additional 10 classrooms. This addition is necessary to meet class size reduction requirements.
This change order provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.14 | |
Hillsborough County Public Schools (Florida) * Mtg.#20090714_356 * Section A Item# 6.14 |