Approve Change Order No. 2 in the Amount of $26,824.25 Extra and a Time Extension of 10 Calendar Days for Kitchen Renovation at
Riverview Elementary School

EXECUTIVE SUMMARY

On February 13, 2007, the Board appointed Schenkel Shultz Architecture and Halfacre Construction Company to provide design and construction management services for renovation of Riverview Elementary School. The renovation of the kitchen includes expansion of the servery, remodeling of the staff toilets to comply with the Americans with Disabilities Act, replacement of all food service equipment, replacement of all interior finishes, and a dumpster enclosure.

This change order provides for structural repairs necessitated by unforeseen conditions discovered by the construction manager during demolition of the kitchen floor. A time extension is included for completion of the work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07 ($362,358) and 1998 Capital Improvement Revenue Bonds ($137,448).

Contract Status:
Guaranteed Maximum Price: $499,806.00
Change Order Previously Approved: $157,681.32 Credit
Change Order Recommended Herein: $26,824.25 Extra
Revised Guaranteed Maximum Price: $368,948.93
Revised Construction Cost: $517,004.51

Original Completion Date: August 7, 2009
Time Extension Recommended Herein: 10 Calendar Days
Revised Completion Date: August 17, 2009

EVALUATION

SUBMITTED BY: James Lipsey, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.06
Hillsborough County Public Schools (Florida) * Mtg.#20090818_359 * Section A Item# 6.06