Facilities Action Item |
DATE: Tuesday, October 6, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Reliable Group Architects was selected from the approved Continuing Services Consultants list to provide design services. On April 21, 2009, the Board awarded the contract for construction to Anderson & Shah Roofing, Inc. to provide construction management services. The scope of work provides for roof, edge metal, and roof drain replacement on selected buildings.
Change Order No. 1 provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program. Change Order No. 2 provides for revisions to the storm gutter installation details and relocation of an air conditioning unit, required due to unforeseen conditions.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Hung Pham, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.15 | |
Hillsborough County Public Schools (Florida) * Mtg.#20091006_362 * Section A Item# 6.15 |