Facilities Action Item |
DATE: Tuesday, November 3, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On July 17, 2007, the Board approved the amendment of agreements with Holmes Hepner and Associates Architects and J.O. DeLotto & Sons, Inc., the architect and construction manager of record for the classroom addition at Burnett Middle School, to include interior and exterior painting and flooring replacement.
This change order provides credits for project savings, return of unused contingency funds, and final reconciliation of the Direct Purchase Program.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.13 | |
Hillsborough County Public Schools (Florida) * Mtg.#20091103_364 * Section A Item# 6.13 |