Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 8, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Schematic Design and Design Development Phases for Renovation at
Trapnell Elementary School

EXECUTIVE SUMMARY

On April 21, 2008, the Board appointed The Architectural Practice, Inc. and Halfacre Construction Company to provide design and construction management services. The renovation of existing facilities will include replacement of the heating, ventilating, and air conditioning (HVAC) system; ceilings and lighting; selected doors and windows; plumbing fixtures; canopies and roof; the electrical distribution system; and existing fencing, paving and site lighting. Project completion is scheduled for November 2010.

Approval of the schematic design and design development phases will allow the architect to proceed with construction documents.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

The project is currently funded at $3,173,000. The estimate of probable cost is $3,172,302. This item is included in the District Capital Outlay: Local Millage.

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.03
Hillsborough County Public Schools (Florida) * Mtg.#20091208_367 * Section A Item# 6.03