Facilities Action Item |
DATE: Tuesday, January 12, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 18, 2008, the Board appointed the architectural firm of Harvard Jolly, Inc. to provide design services. On May 5, 2009 the Board awarded the contract for construction to Southern Roofing Company, Inc. The scope of work provides for replacement of the existing roof and skylights at Chamberlain High School.
Change Order No. 1 provides for final reconciliation of the Direct Purchase Program. Change Order No. 2 provides a credit for the return of unused contingency funds.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.05 | |
Hillsborough County Public Schools (Florida) * Mtg.#20100112_390 * Section A Item# 6.05 |