Facilities Action Item |
DATE: Tuesday, January 12, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Wilder Architecture, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 19, 2009, the Board awarded the contract for construction to Eveland Brothers, Inc. The scope of work included bleacher modifications, structural repairs, and re-roofing of the stadium.
Change Order No. 1 provides a credit for damages to the track and field caused by the contractor. Change Order No. 2 provides a credit for project savings and the return of unused contingency funds.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.09 | |
Hillsborough County Public Schools (Florida) * Mtg.#20100112_390 * Section A Item# 6.09 |