Approve Acceptance of Project for Classroom Addition at Tomlin Middle School
EXECUTIVE SUMMARY

On July 15, 2008, the Board appointed Long & Associates Architects/Engineers, Inc. and J.O. DeLotto & Sons, Inc. to provide design and construction management services. The scope of work provided for an additional 16 classrooms. This addition was necessary to meet class size reduction requirements.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

This item was included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,692,500.00
Approved Change Orders: $526,595.84 Credit (See Attachment)
Revised Guaranteed Maximum Price: $2,165,904.16
Payments to Date:  $2,142,327.59
Balance Due:  $23,576.57
Revised Construction Cost: $2,633,494.55

Required Substantial Completion Date: August 17, 2009
Approved Time Extension : 30 Calendar Days (See Attachment)
Revised Required Substantial Completion Date: September 16, 2009
Substantial Completion Date:  September 10, 2009

EVALUATION
SUBMITTED BY:  Jill Edwards, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
813-272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.08e
Hillsborough County Public Schools (Florida) * Mtg.#20101116_431 (Board Meeting) * Section A Item# 6.08e