SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for Renovation at Pinecrest Elementary School | |
EXECUTIVE SUMMARY | |
On February 13, 2007, the Board appointed Howard & Associates Architects, P.A. and J.O. DeLotto & Sons, Inc. to provide design and construction management services. The renovation of existing facilities included new fire sprinklers, door hardware, and window blinds; upgrade of interior partitions to satisfy fire code requirements; signage; fencing of selected areas; canopy and sidewalk repair; interior and exterior painting; repair of selected windows and doors; refacing of selected casework; replacement of selected roofing, plumbing fixtures, and flooring; and replacement of lighting, ceilings, low voltage systems, chalkboards, toilet partitions and accessories, and heating, ventilating, and air conditioning (HVAC) chillers. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07. Contract Status: Required Substantial Completion Date: December 15, 2008 |
|
EVALUATION | |
SUBMITTED BY: Jill Edwards, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |