HCPS FL Logo Facilities
Action Item
DATE: Tuesday, December 7, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Cafeteria HVAC, Window and Storefront Replacement at Seminole Elementary School
EXECUTIVE SUMMARY

Woodroffe Corporation Architects and Greater Bay Construction Company, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services.  The scope of work provided for replacement of the cafeteria heating, ventilating, and air conditioning (HVAC) system, storefront and windows at Seminole Elementary School.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

Due to the failure of Greater Bay Construction to complete the contract requirements, the Board recently terminated the agreement with Greater Bay for this project.  Staff is working with the Board attorney to determine the appropriate disposition of the remaining funds due. 

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item was included in the District Capital Outlay: Local Millage.

Contract Status:
Guaranteed Maximum Price: $575,220.97
Approved Change Order: $86,101.72 Credit (See Attachment)
Revised Guaranteed Maximum Price: $489,119.25
Payments to Date: $463,036.34
Balance Due: $26,082.91
Revised Construction Cost: $568,684.03

Required Substantial Completion Date: August 27, 2008
Substantial Completion Date: September 30, 2008

EVALUATION
SUBMITTED BY:  Clay Ward, Facilities Maintenance Support Manager
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.10f
Hillsborough County Public Schools (Florida) * Mtg.#20101207_432 (Board Meeting) * Section A Item# 6.10f