Facilities
Action Item |
DATE: | Tuesday, December 7, 2010 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for Cafeteria HVAC, Window and Storefront Replacement at Seminole Elementary School | |
EXECUTIVE SUMMARY | |
Woodroffe Corporation Architects and Greater Bay Construction Company, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provided for replacement of the cafeteria heating, ventilating, and air conditioning (HVAC) system, storefront and windows at Seminole Elementary School. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance. Due to the failure of Greater Bay Construction to complete the contract requirements, the Board recently terminated the agreement with Greater Bay for this project. Staff is working with the Board attorney to determine the appropriate disposition of the remaining funds due. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage.
Contract Status: Required Substantial Completion Date: August 27, 2008 |
|
EVALUATION | |
SUBMITTED BY: Clay Ward, Facilities Maintenance Support Manager |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|