Approve Acceptance of Project for Renovation at West Shore Elementary School | |
EXECUTIVE SUMMARY | |
On February 13, 2007, the Board appointed Rowe Architects, Inc. and J.B.D. Construction, Inc. to provide design and construction management services. The renovation of existing facilities included roof and plaster wall repairs; exterior brick repointing, restoration, and sealing; interior painting; upgrades to emergency lighting, telephone, voice/data, closed circuit television (CCTV), and security systems; replacement of the fire alarm system and instructional aids; removal of carpet and refinishing of existing hardwood floors; handicap accessibility upgrades to door hardware, thresholds, and building entries; and the addition of a fire sprinkler system. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage. |
|
EVALUATION | |
SUBMITTED BY: Alice Sutton, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4122 |
Chief Facilities Officer (813) 272-4004 |
|