Approve Acceptance of Project for Heating, Ventilating, and Air Conditioning (HVAC) Improvements at Temple Terrace Elementary School
EXECUTIVE SUMMARY

RHC and Associates, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 19, 2009, the Board awarded the contract for construction to the low bidder, B & I Contractors, Inc. The scope of work provided for replacement of the chiller, air handlers and associated piping and pumps; and cleaning of related ducts for Building 13 (multipurpose/student dining), Building 5 (music/classrooms) and Building 14 (mechanical/central receiving).

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item was included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $329,000.00
Approved Change Order: $18,033.71 Credit (See Attachment)
Revised Contract Sum: $310,966.29
Payments to Date: $304,999.52
Balance Due: $5,966.77
Revised Construction Cost: $377,113.29

Required Substantial Completion Date: August 7, 2009
Approved Time Extension: 10 Calendar Days (See Attachment)
Revised Required Substantial Completion Date: August 17, 2009
Substantial Completion Date: August 7, 2009

EVALUATION
SUBMITTED BY:  Alice Sutton, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.08c
Hillsborough County Public Schools (Florida) * Mtg.#20110718_467 (Board Meeting) * Section A Item# 6.08c