Approve Change Order Nos. 1 and 2 for Child Care Facility Addition at South County Career Center | |
EXECUTIVE SUMMARY | |
To establish a Teen Parent Program at South County Career Center, remodeling of a portion of the facility was needed to support requirements for a child care center. Long & Associates Architects/Engineers, Inc. was selected from the approved Continuing Services Consultants list to provide design services for the remodeling. The project was publicly advertised and bids were received. District staff awarded the contract for construction to the low bidder, K C Jensen Construction, Inc. Change Order No. 1 provides miscellaneous changes to support childcare facility requirements; plumbing modifications required due to unforeseen conditions; and a credit for liquidated damages for late completion. A two calendar day time extension is included for completion of the work. Change Order No. 2 provides for additional plumbing revisions required due to unforeseen conditions. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item is included in the District Capital Outlay: Local Millage.
Contract Status: Required Substantial Completion Date: August 30, 2010 |
|
EVALUATION | |
SUBMITTED BY: Clay Ward, Facilities Support Manager |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.05 | ||