Action Item
DATE: Tuesday, July 26, 2011
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Tentative District Five-Year Work Plan
EXECUTIVE SUMMARY

Florida Statute requires each school district to develop and approve a district five-year capital outlay work plan.  The plan must be submitted to the Department of Education prior to October 1st of each year.  The plan must include a schedule of all major repairs, renovations and new construction projects planned and include information about class size and the use of portable classrooms in the school district.  The capital outlay revenue of the district must also be projected.  The Capital Outlay Full Time Equivalent (COFTE) projections are based upon cohort projections from the annual live birth rates within the school district and this year the projections reflect the changes in State policies with respect to growth in charter and virtual schools, mandatory virtual classes, and an expanded McKay scholarship program.

As required by our interlocal agreements with the local governments, after the tentative work plan is approved by the Board, the work plan is reviewed and discussed with other public agencies, including Hillsborough County, the Planning Commission and the cities of Tampa, Plant City and Temple Terrace.  These reviewing entities have 45 days to provide comments to the District.  As appropriate, these recommendations are included in a revised plan that will come to the Board for final approval at the September 20, 2011 Board meeting and will be transmitted to the Department of Education for review.  The plan can be changed by Board action at a noticed meeting at which the public has an opportunity to comment.

STRATEGIC OBJECTIVES
• Align financial resources to support the district’s strategic goals • Demonstrate best financial practices • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

The Plan identifies $129,322,365 in funded maintenance and major repair projects.  An additional $95,701,707 in new construction projects is identified of which $29,100,000 will be used toward funding a middle school to be constructed beyond the current plan time-horizon.  Sufficient revenue is projected to be available for listed projects.  Renovation and remodeling projects totaling $119,443,663 are unfunded.

EVALUATION
SUBMITTED BY: 
Lorraine Duffy Suarez   Cathy L. Valdes
General Manager, Growth Mgmt. & Planning
(813) 272-4685
  Chief Facilities Officer
(813) 272-4004
    A 6.04
Hillsborough County Public Schools (Florida) * Mtg.#20110726_468 (Board Meeting followed by Public Hearing) * Section A Item# 6.04