HCPS FL Logo Facilities
Action Item
DATE: Tuesday, September 20, 2011
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at Lewis Elementary School
EXECUTIVE SUMMARY

The approved District Five Year Plan included the project for renovation of the heating, ventilating, and air conditioning (HVAC) system at Lewis Elementary School. On October 5, 2010, the Board appointed Ossi Consulting Engineers, Inc. to provide design services. On May 17, 2011, the Board awarded the contract for construction to J.R. Long, Inc.  The scope of work provided for new ductwork; replacement of the existing air handlers; replacement of lighting and acoustical ceilings; a new energy management control system; a new fire sprinkler system; and renovation of the existing data network and security systems.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $2,036,720.00
Approved Change Orders: $224,736.28 Credit (See Attachment)
Revised Contract Sum: $1,811,983.72
Payments to Date: $937,896.55
Balance Due: $874,087.17
Revised Construction Cost: $2,146,892.47

Required Substantial Completion Date: August 11, 2011
Substantial Completion Date: August 11, 2011

EVALUATION
SUBMITTED BY:  Alice Sutton, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004