Facilities
Action Item |
DATE: | Tuesday, November 8, 2011 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for Stage Lighting Replacement at Blake High School | |
EXECUTIVE SUMMARY | |
The approved District Five Year Plan included a project for renovation of the stage lighting at Blake High School. District staff selected Tanase & Associates, Inc. & KBA Engineering, Inc. from the approved Continuing Services Consultants list to provide design services. On June 14, 2011, the Board awarded the contract for construction to D&S Electrical Technologies, LLC. The scope of work provided for the replacement of the existing theatrical stage lighting system. The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage.
Contract Status: Required Substantial Completion Date: September 5, 2011
|
|
EVALUATION | |
SUBMITTED BY: John Williams, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.02 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20111108_507 (Board Meeting) * Section A Item# 6.02 |