Action Item
DATE: Tuesday, April 23, 2013
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Change Order No. 4-R1 for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at Twin Lakes Elementary School
EXECUTIVE SUMMARY

On October 26, 2010, the Board approved the issuance of approximately $37,935,000 of Qualified School Construction Bonds (QSCBs) for renovation of roofs and heating, ventilating, and air conditioning (HVAC) systems at various District sites. The QSCBs provided for acceleration of roof and HVAC renovations previously scheduled in the five-year plan, including renovation of the HVAC system at Twin Lakes Elementary School. (The allocation of QSCB funded projects to phases is indicated in an attachment.)

On June 14, 2011, the Board appointed VoltAir Consulting Engineers, LLC to provide design services for the project at Twin Lakes. On April 10, 2012, the Board awarded the contract for construction to the low bidder, Vogel Bros. Building Co.

Pursuant to Board policy, staff issued construction change directives (CCD) as listed in the attachments to address several unforeseen conditions, code official requirements, and design deficiencies that arose during the summer construction period.  The policy requires that normal change order procedures be implemented following issuance of a CCD.   As this change order is for an amount greater than $100,000, Board approval is required.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item is included in the District Capital Outlay: Qualified School Construction Bonds.

Contract Status:
Contract Sum:  $2,775,000.00
Approved Change Orders: $627,038.11 Credit (See Attachment)
Change Order Recommended Herein: $132,630.88 Extra (See Attachment)
Revised Contract Sum: $2,280,592.77

Required Substantial Completion Date: August 12, 2012
EVALUATION
SUBMITTED BY:  John Williams, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.05
Hillsborough County Public Schools (Florida) * Mtg.#20130423_560 (Board Meeting) * Section A Item# 7.05