Facilities
Action Item |
DATE: | Tuesday, May 21, 2013 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Construction Documents and Guaranteed Maximum Price for Renovation of the Heating, Ventilating and Air Conditioning (HVAC) System at Velasco Student Services Building | |
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provides for renovation of the HVAC system at the Velasco Student Services Building. District staff selected Carastro & Associates, Inc. and Vogel Bros. Building Company from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for replacement of the existing HVAC system and connection of the system to chilled water being purchased from Ybor District Cooling. (The Board previously approved the agreement for the purchase of chilled water.) Interior repainting and replacement of the existing ceiling, lights, and carpet is also included. Project completion is scheduled for October 29, 2013. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Total construction cost is warranted at $1,801,382. The construction budget is $1,802,000. This item is included in the District Capital Outlay: Local Millage. |
|
EVALUATION | |
SUBMITTED BY: Alice Sutton, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 7.14 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20130521_564 (Board Meeting) * Section A Item# 7.14 |