Facilities
Action Item |
DATE: | Tuesday, January 21, 2014 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Design Development for Renovation of Boyette Springs Elementary School | |
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provides for the renovation of Boyette Springs Elementary School. On October 8, 2013 the Board appointed Wilder Architecture, Inc. and Skanska USA Building, Inc. to provide design and construction management services.
The proposed scope of work includes renovation of the heating, ventilating, and air conditioning (HVAC) system; resurfacing of asphalt parking lots and drives; replacement of exterior pole mounted light fixtures; new energy-efficient lighting; new ceilings and carpet; new signage; new security and fire alarm systems; a new fire sprinkler system; and correction of accessibility and safety deficiencies. Approval of design development as illustrated in the attachment will allow the design professional to proceed with construction documents. Project completion is scheduled for August 2014. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: No) | |
Construction budget is $5,089,208. This item is included in the District Capital Outlay: Local Millage. | |
EVALUATION | |
SUBMITTED BY: Hung Pham, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 7.06 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20140121_624 (Board Meeting) * Section A Item# 7.06 |