Approve Acceptance of Project for Roof Replacement at Three Sites (Lanier, Mendenhall, Lois Center) | |
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provided for replacement of selected roof areas at Lanier and Mendenhall Elementary Schools, and the main office and walkway canopies of the District's Customer Service and Support Department at the Lois Center. District staff selected Weber & Tinnen, P.A. from the approved Continuing Services Consultants list to provide design services. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage. |
|
EVALUATION | |
This item was included in the District Capital Outlay: Local Millage. Contract Status: Contract Sum: $712,470.00 Approved Change Orders: $252,420.96 Credit (See attachment) Revised Contract Sum: $460,049.04 Payments to Date: $410,745.80 Balance Due: $49,303.24 Revised Construction Cost: $658,862.23 Required Substantial Completion Date: August 4, 2013 Approved Time Extension: 64 Calendar Days Revised Required Substantial Completion Date: October 4, 2013 Substantial Completion Date: October 4, 2013 |
|
SUBMITTED BY: Alice Sutton, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Deputy Superintendent (813) 272-4899 |
|
A 7.03 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20140318_629 (Board Meeting) * Section A Item# 7.03 |