HCPS FL Logo Facilities
Action Item
DATE: Tuesday, April 29, 2014
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Construction Documents and Guaranteed Maximum Price for Building Envelope and Interior Renovation at Hill Middle School
EXECUTIVE SUMMARY

On July 30, 2013, the Board appointed C. B. Goldsmith and Associates, Inc. and Walbridge-Aldinger Company to provide design and construction management services for a project to address water intrusion and the potential failure of the brick exterior at Hill Middle School. 

The scope of work includes removal of the brick on selected exterior walls and replacement with a thin brick system matching the existing appearance. Repair of corroded structural members and replacement of selected exterior windows and doors is included in the project scope.  (The recommended wall system will provide greater insulation than currently exists, yielding long-term energy cost savings)  The scope also includes minor interior renovations (painting, whiteboards, lockers) and remodeling that complete the renovation requirements at the school. Project completion is scheduled for August 7, 2015.

Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
Total construction cost is warranted as $8,821,623.  The construction budget is $8,822,000.  This item is included in the District Capital Outlay:  Local Millage.
EVALUATION
SUBMITTED BY:  John Williams, Project Coordinator
Rory A. Salimbene   Christopher Farkas
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004