HCPS FL Logo Facilities
Action Item
DATE: Tuesday, May 19, 2015
TO: School Board Members
FROM: Jeff Eakins, Acting Superintendent
SUBJECT / RECOMMENDATIONS

Approve Construction Documents and Guaranteed Maximum Price (GMP) for Exterior Painting and Building Envelope Renovations at Four Sites (Corr, Collins, Folsom and Valrico Elementary Schools)

EXECUTIVE SUMMARY
A previously approved District Facilities Five Year Work Program provides for exterior painting and building envelope renovations at Corr, Collins, Folsom and Valrico Elementary Schools.  District staff combined the requirements into a single project and selected C.B. Goldsmith and Associates, Inc. and Vogel Bros. Building Co. from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work includes window, sealant and stucco repairs; walkway traffic coatings; and exterior painting at each school.

Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project.

Project completion is scheduled for August 2015.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

Total construction cost is warranted at $3,110,330. Funds for this item are included in District Capital Outlay: Local Millage.

EVALUATION
SUBMITTED BY:  Hung Pham, Project Coordinator
Rory A. Salimbene   Christopher Farkas
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.04