Business Services
Action Item |
| DATE: | Tuesday, March 12, 2019 |
| TO: | School Board Members |
| FROM: | Jeff Eakins, Superintendent |
| SUBJECT / RECOMMENDATIONS | |
| Approve Amendments Nine and Ten of the No Capital Outlay Plan Agreement with Minimise, USA, LLC, for the Energy Management Project (Business Services Division) (Revision to Attachment: combined prior attachments; signature pages added; correction to page 9) | |
| EXECUTIVE SUMMARY | |
The No Capital Outlay Plan Agreement is being updated through:
|
|
| STRATEGIC OBJECTIVES | |
| • Establish a strong foundation of financial stewardship | |
| FINANCIAL IMPACT (Budgeted: No) | |
| EVALUATION | |
| August 1, 2017 - Memorandum of Agreement Energy Survey, Minimise, USA, LLC November 14, 2017 - Exhibit Items and progress of work update January 2018 - Agreement for Scope of Work (estimate of plan and savings) February 20 - July 17, 2018 - Various Amendments to update Shared Savings Plan Agreement December 4, 2018 - Amendment Eight, pre-paid energy savings check and Edison Elementary School technology presentation |
|
| SUBMITTED BY: | |
| Christopher Farkas | Gretchen Saunders | |
| Deputy Superintendent, Operations (813) 272-4004 |
Chief Business Officer (813) 272-4270 |
|
| C 6.10R | ||
| Hillsborough County Public Schools (Florida) * Mtg.#20190312_919 (Board Meeting) * Section C Item# 6.10R | ||