HCPS FL Logo Operations
Action Item
DATE: Tuesday, July 16, 2019
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Guaranteed Maximum Price (GMP) for Interior Security Wall Modifications at Bellamy Elementary School (Operations Division)
EXECUTIVE SUMMARY
As part of a recent security assessment, District staff selected Renker, Eich, Parks Architects, Inc. and Ajax Building Corporation from the approved continuing services consultants list to provide design and construction management services, respectively. The scope of work provides for interior renovation with security and acoustical separation of the classrooms at Bellamy Elementary School. 
 
Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project.

Project completion is scheduled for March 10, 2020.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
The GMP recommended for approval is $1,994,693, which is available in the Local Millage fund.
EVALUATION
SUBMITTED BY:  Carin Hunt, Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.05
Hillsborough County Public Schools (Florida) * Mtg.#20190716_927 (Board Meeting) * Section B Item# 7.05