Operations
Action Item |
DATE: | Tuesday, June 11, 2019 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Guaranteed Maximum Price (GMP) for Heating, Ventilating and Air Conditioning (HVAC) at Potter Elementary School Cafeteria (Operations Division) |
|
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provides for HVAC replacement at Potter Elementary School Cafeteria. District staff selected RHC and Associates, Inc. and R. W. Tymewell, Inc. from the approved Continuing Services Consultants list to provide design and construction management services, respectively. The project scope consists of the installation of four packaged roof top units and existing mini-split systems, replacement of ceilings throughout the cafeteria, structural steel framing and new ductwork.
Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project Projects completion is scheduled for August 1, 2019. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The Guaranteed Maximum Price recommended for approval is $389,305, which is available in the Local Millage fund.
|
|
EVALUATION | |
SUBMITTED BY: Chuck Plante, Sr. Project Administrator |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||
B 7.10 | ||