HCPS FL Logo Operations
Action Item
DATE: Tuesday, June 11, 2019
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Guaranteed Maximum Price (GMP) for Phase 1 of the Reconstruction at Tampa Heights Elementary School (Operations Division)
EXECUTIVE SUMMARY
On October 2, 2018, the Board approved the appointment of Fleischman-Garcia Architects and Planners, AIA, PA and J.E. Dunn Construction Company to provide design and construction management services, respectively.

In an effort to improve the overall construction schedule, the project has been divided in two phases.  The design has now progressed to the point where Phase 1, consisting of demolition, foundation and structural components, can commence.

Approval of the Phase 1 Guaranteed Maximum price (GMP) will establish the maximum cost for this phase of the project.

Phase 1 project completion is scheduled for November 30, 2019.  Overall project completion is scheduled for November 23, 2020.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  No)
The Guaranteed Maximum Price recommended for approval is $3,214,904, which will be reimbursed by Insurance.
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.08