Approve Award of Contract for Roof Replacement at Hunter's Green Elementary School (Operations Division) |
|
EXECUTIVE SUMMARY | |
The District's referendum advertisement provides for several roof replacements within the District. The scope of work includes roof replacements of the main campus apart from Classrooms for Kids (CFK) and playcourt areas at Hunter's Green Elementary School. The project was advertised and bids received (see attached bid tabulation). Award of the contract for construction to the lowest qualified bidder, Springer-Peterson Roofing & Sheet Metal, Inc., is recommended. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The contract amount being awarded is $1,011,871, which is available in the Sales Tax Referendum fund.
|
|
EVALUATION | |
SUBMITTED BY: Ben Moore, Sr. Department Manager |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||