Operations
Action Item |
DATE: | Tuesday, September 10, 2019 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Guaranteed Maximum Price (GMP) for Elementary D (Operations Division) |
|
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provides for a new elementary school in southern Hillsborough County to ensure the availability of satisfactory classrooms for projected student enrollment in K-12 programs for the 2020/21 school year. In conjunction with Elementary C that opened for the 2017/18 school year, Elementary D will assist in relieving current or projected overcrowding at Sessums, Collins, Boyette Springs and Stowers Elementary Schools (other Area 8 schools may be impacted). On October 4, 2016, the Board appointed Holmes Hepner Architects, Inc. and Allstate Construction, Inc. to provide design and construction management services.
Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project.
Project completion is scheduled for August 3, 2020. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The GMP recommended for approval is $22,747,948, which is available in the Impact Fee fund.
|
|
EVALUATION | |
SUBMITTED BY: Carin Hunt, Project Administrator |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||
C 7.06 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20190910_930 (Board Meeting followed by Public Hearing) * Section C Item# 7.06 |