DATE: Tuesday, November 19, 2019
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Guaranteed Maximum Price (GMP) for the Fire Damage Demolition Project at McLane Middle School (Operations Division)
EXECUTIVE SUMMARY
On July 19, 2019, fire damaged Building Number 600 at McLane Middle School.  District staff selected Master Consulting Engineers, Inc. and HCBeck, Ltd. dba The Beck Group from the approved Continuing Services Consultants list to provide design and construction management services.  The scope of work provides for the demolition and removal of this building.

Approval of the GMP will establish the cost for the project.

Project completion is scheduled for November 30, 2019.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
The GMP recommended for approval is $717,337, which will be reimbursed by insurance.
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.08