The HVAC System in the Plant High School Gymnasium had been malfunctioning for quite some time.  District staff selected Carastro & Associates, Inc. and Reno Building, LLC from the approved Continuing Services Consultants List to provide design and construction management services to replace the HVAC system.  The project scope consisted of the replacement of three HVAC units in the Gymnasium, addition of variable frequency drives added to the existing boys and girls restrooms and the associated transfer fans..

The design professional has certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item is available in the Community Investment Tax fund.

Contract Status:
Contract Sum:  $680,175.00
Approved Change Orders:  $297,243.29 Credit (See Attachment)
Revised Contract Sum:  $382,931.71
Payments to Date:  $357,789.32
Balance Due:  $25,142.39
Revised Construction Cost:  $612,895.71

Required Substantial Completion Date:  April 26, 2019
Approved Time Extension:  59 Calendar Days
Revised required Substantial Completion Date:  June 24, 2019
Substantial Completion Date:  June 24, 2019

 
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.13
Hillsborough County Public Schools (Florida) * Mtg.#20191119_933 (Reorganization/Board Meeting) * Section B Item# 7.13