Action Item
DATE: Tuesday, November 19, 2019
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
 Approve Acceptance of Project for the Referendum Phase One Project at Folsom Elementary School (Operations Division)
EXECUTIVE SUMMARY
The District's referendum advertisement provided for partial heating, ventilating and air conditioning (HVAC) replacement at Folsom Elementary School.  On February 5, 2019, District staff selected Ossi Consulting Engineering, Inc. and Wharton-Smith, Inc. to provide design and construction management services, respectively, through a selection committee.  Award was made based upon the score granted by the selection committee.  Due to the magnitude of the scope of work, this project was divided into two phases.

The design professional has certified that the Phase 1 work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item is available in the Sales Tax Referendum fund.

Contract Status:
Guaranteed Maximum Price: $1,250,882.00
Approved Change Orders:  $247,340.75 Credit (See Attachment)
Revised Guaranteed Maximum Price: $1,003,541.25
Payments to Date:  $944,180.40
Balance Due:  $59,360.85
Revised Construction Cost:  $1,161,647.25
 
Required Substantial Completion Date:  August 1, 2019
Substantial Completion Date:  August 1, 2019
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.11
Hillsborough County Public Schools (Florida) * Mtg.#20191119_933 (Reorganization/Board Meeting) * Section B Item# 7.11