SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Roof Replacement at Schwarzkopf Elementary School (Operations Division)

EXECUTIVE SUMMARY
A previously approved District Facilities Five Year Work Program provided for roof replacement at Schwarzkopf Elementary School.  District staff selected C. B. Goldsmith & Associates, Inc. to provide design services.  On May 15, 2018, the Board appointed Springer-Peterson Roofing & Sheet Metal, Inc. to provide construction management services.

The design professional and roofing manufacturer (for the 20 year warranty) have certified that the work is now fully complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item is available in the Local Millage and PECO Maintenance funds.

Contract Status:
Contract Sum:  $946,820.00
Approved Change Orders:  $252,539.77 Credit (See Attachment)
Revised Contract Sum:  $694,280.23
Payments to Date:  $610,167.73
Balance Due:  $84,112.50
Revised Construction Cost:  $897,947.84

Required Substantial Completion Date:  September 24, 2018
Substantial Completion Date:  September 24, 2018
EVALUATION
SUBMITTED BY:  Ben Moore, Sr. Department Manager
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.07
Hillsborough County Public Schools (Florida) * Mtg.#20191210_935 (Board Meeting) * Section B Item# 7.07