Approve Guaranteed Maximum Price (GMP) for the Referendum Phase Two Project at Colson Elementary School (Operations Division)
EXECUTIVE SUMMARY
On February 5, 2019, District staff selected VoltAir Consulting Engineers, LLC and Halfacre Construction Company to provide design and construction management services, respectively, through a selection committee.  Award was made based upon the score granted by the selection committee.  Due to the magnitude of the scope of work, this project has been divided into two phases at Colson Elementary School.

In an effort to improve the air conditioning performance, the project has been divided in two phases.  Phase One consisted of the replacement of heating, ventilating and air conditioning (HVAC) equipment and built-up roofing.  Phase Two of the project includes the replacement of metal roofing and the ductwork in Buildings 1, 3, 5 and 8 which will complete the HVAC upgrade at that school.

Approval of the Phase Two Guaranteed Maximum Price (GMP) will establish the maximum cost for this phase of the project.

Phase Two project substantial completion is currently scheduled for August 3, 2020.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
The Guaranteed Maximum Price (GMP) recommended for approval for Phase Two is $2,123,076, which is in the Sales Tax Referendum fund.
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004