HCPS FL Logo Operations
Action Item
DATE: Tuesday, February 18, 2020
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Guaranteed Maximum Price (GMP) for Interior Wall Reconfigurations - Phase Two at Bellamy Elementary School (Operations Division)
EXECUTIVE SUMMARY
As part of a recent security assessment, District staff selected Renker, Eich, Parks Architects, Inc. from the approved Continuing Services Consultants list to provide design services.  Core Construction Services of Florida, Inc. was chosen through a selection committee to provide construction management services.  Phase Two scope of work provides for reconfiguring walls to provide lockable classrooms, exterior painting and heating, ventilating and air conditioning (HVAC) replacement at Bellamy Elementary School. 
 
Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project.

Project completion is scheduled for July 28, 2020.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
The GMP recommended for approval is $3,679,429, which is available in the Capital Outlay and Debt Service (CO & DS) fund.
EVALUATION
SUBMITTED BY:  Carin Hunt, Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    B 7.03