Operations
Action Item |
DATE: | Tuesday, February 18, 2020 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Guaranteed Maximum Price (GMP) for Interior Wall Reconfigurations - Phase Two at Bellamy Elementary School (Operations Division) |
|
EXECUTIVE SUMMARY | |
As part of a recent security assessment, District staff selected Renker, Eich, Parks Architects, Inc. from the approved Continuing Services Consultants list to provide design services. Core Construction Services of Florida, Inc. was chosen through a selection committee to provide construction management services. Phase Two scope of work provides for reconfiguring walls to provide lockable classrooms, exterior painting and heating, ventilating and air conditioning (HVAC) replacement at Bellamy Elementary School. Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project. Project completion is scheduled for July 28, 2020. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The GMP recommended for approval is $3,679,429, which is available in the Capital Outlay and Debt Service (CO & DS) fund.
|
|
EVALUATION | |
SUBMITTED BY: Carin Hunt, Project Administrator |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||
B 7.03 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20200218_979 (Board Meeting) * Section B Item# 7.03 |