Operations
Action Item |
DATE: | Tuesday, March 31, 2020 |
TO: | School Board Members |
FROM: | Addison Davis, Acting Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Guaranteed Maximum Price (GMP) for the Referendum (Year Two) Project at Bevis Elementary School <em><strong>(Operations Division)</strong></em> | |
EXECUTIVE SUMMARY | |
On February 5, 2019, District staff selected BAL Engineering, Inc. and Reno Building, LLC to provide design and construction management services, respectively, through a selection committee. Award was made based upon the score granted by the selection committee. The project scope consisted of partial heating, ventilating and air conditioning (HVAC) replacement. <br /><br /> Approval of the GMP will establish the cost for the project. <br /><br /> Project substantial completion is scheduled for July 31, 2020. | |
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship, • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health, • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The GMP recommended for approval is $3,042,447, which is available in the Sales Tax Referendum fund.
|
|
EVALUATION | |
N/A | |
SUBMITTED BY: Chuck Plante, Sr. Project Administrator |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||
B 7.05 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20200331_1016 (Board Meeting) * Section B Item# 7.05 |