HCPS FL Logo Operations
Item
DATE: Tuesday, June 23, 2020
TO: School Board Members
FROM: Addison Davis, Acting Superintendent
SUBJECT / RECOMMENDATIONS
<p style="text-align: justify;">Approve Guaranteed Maximum Price (GMP) for Referendum (Year Two) Project at Plant High School <em>(Operations Division)</em></p>
EXECUTIVE SUMMARY
<p style="text-align: justify;">The District's referendum advertisement provided for various heating, ventilating and air conditioning (HVAC) upgrades and replacements.&nbsp; District staff selected Minimise USA Capital, LLC, in accordance with the terms of the existing No Capital Outlay Plan Agreement (NCOPA), to provide the necessary design and construction management services for selected projects.&nbsp; The scope of work provides for complete HVAC replacement in multiple buildings&nbsp;at Plant High School.</p> <p style="text-align: justify;">Approval of the GMP will establish the cost for the entire project.</p> <p style="text-align: justify;">Project Substantial Completion is scheduled for August 6, 2021.</p>
STRATEGIC OBJECTIVES
<p>• Establish a strong foundation of financial stewardship</p> <p>• Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health</p> <p>• Construct and maintain facilities that create an environment conducive to teaching and learning</p>
FINANCIAL IMPACT (Budgeted:  No)
EVALUATION
SUBMITTED BY:  Chuck Plante, Sr. Project Administrator, chuck.plante@hcps.net, (813) 272-4112
    Christopher Farkas

  Chief Operating Officer
(813) 272-4004
    B 7.12
Hillsborough County Public Schools (Florida) * Mtg.#20200623_1005 (Board Meeting) * Section B Item# 7.12