Hillsborough County Public Schools, Florida
Tuesday, 04/28/2020
School Board Meeting
Title

B7.16 - Approve Acceptance of Project for Referendum (Year One) Project at Schwarzkopf Elementary School (Operations Division)

Description

On February 5, 2019, District staff selected Consulting Engineering Associates, Inc. and Ajax Building Corporation to provide design and construction management services, respectively, through a selection committee.  Award was made based upon the score granted by the selection committee.  The project scope consisted of partial heating, ventilating and air conditioning (HVAC) and stage equipment replacements at Schwarzkopf Elementary School.

The design professional has certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

Gap Analysis

N/A

Previous Outcomes

N/A

Expected Outcomes

Execution of a major construction project that will result in an energy-efficient HVAC system (partial) replacement at Schwarzkopf Elementary School.

Strategic Plan Goal

Create a greatly improved learning environment for the students at Schwarzkopf Elementary School.

Recommendation

Approve the Acceptance of Project and release of final payment.

Contact

Carin Hunt, Project Administrator, carin.hunt@sdhc.k12.fl.us, (813) 272-4112

Financial Impact

This item is available in the Sales Tax Referendum fund.

Contract Status:

Guaranteed Maximum Price:  $1,787,016.00

Approved Change Orders:  $548,668.70  Credit (See Attachment)

Revised Guaranteed Maximum Price:  $1,238,347.30

Payments to Date:  $1,218,306.40

Balance Due:  $20,040.90

Revised Construction Cost:  $1,483.308.30

Required Substantial Completion Date:  August 1, 2019

Substantial Completion Date:  August 1, 2019

Review Comments

Christopher Farkas, Deputy Superintendent, Operations (813) 272-4004