B7.16 - Approve Acceptance of Project for Referendum (Year One) Project at Colson Elementary School (Operations Division)
The District's referendum advertisement provided for roof replacement, partial heating, ventilating and air conditioning (HVAC) replacement, stage lighting replacement and electrical upgrades at Colson Elementary School. On February 5, 2019, District staff selected VoltAir Consulting Engineers, LLC and Halfacre Construction Company to provide design and construction management services, respectively, through a selection committee. Award was made based upon the score granted by the selection committee.
Due to the magnitude of the scope of work and the limited time available over the summer months, this project was divided into two phases. The design professional has certified that Phase 1 of the work is complete in accordance with the plans and specifications and other contract documents and, as such, recommends Board Acceptance.
Previously, Colson Elementary School's HVAC and roofing systems were seriously deficient and not performing satisfactorily.
N/A
The school now has a much-improved HVAC system and a new roof over the majority of the school. Phase 2 being performed in the summer of 2020 will totally complete the project.
* Establish a strong foundation of financial stewardship
* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health
* Construct and maintain facilities that create an environment conducive to teaching and learning
Accept Phase 1 of the Colson Elementary HVAC/Roofing project.
Chuck Plante, Sr. Project Administrator, chuck.plante@sdhc.k12.fl.us, (813) 272-4112
This item is available in the Sales Tax Referendum fund.
Contract Status:
Guaranteed Maximum Price: $2,986,526.00
Approved Change Orders: $805,984.23 Credit (See Attachment)
Revised Guaranteed Maximum Price: $2,180,541.77
Payments to Date: $2,169,800.72
Balance Due: $10,741.05
Revised Construction Cost: $2,650,695.19
Required Substantial Completion Date: August 1, 2019
Approved Time Extension: 15 Calendar Days
Revised Required Substantial Completion Date: August 16, 2019
Substantial Completion Date: August 16, 2019