B7.27 - Approve Acceptance of Project for the Painting/Waterproofing at Four Sites (Buchanan, Ferrell, Foster, Just) (Operations Division)

Description

The District's referendum advertisement provided for painting/waterproofing at multiple sites.  District staff selected R.W. Tymewell, Inc from the approved Continuing Services Consultants list to provide construction management services.  The project scope consisted of interior and exterior painting and waterproofing at Buchanan Middle, interior painting at Ferrell Middle, interior and exterior painting and waterproofing at Foster Elementary and interior painting at Just Elementary Schools.

The work is complete in accordance with the plans and specifications and other contract documents and recommend Board Acceptance. 

Gap Analysis

N/A

Previous Outcomes

N/A

Expected Outcomes

N/A

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of the painting/waterproofing project at Buchanan Middle, Ferrell Middle, Foster Elementary and Just Elementary Schools.

Contact

Benjamin Moore, Sr. Department Manager, benjamin.moore@hcps.net, (813) 653-1133

Financial Impact

The item is available in the Sales Tax Referendum fund.

Contract Status:
Guaranteed Maximum Price: $1,999,936.00
Approved Change Orders:  $196,724.79  Extra (See Attachment)
Revised Guaranteed Maximum Price: $2,196,660.79
Payments to Date:  $2,099,704.08
Balance Due:  $96,956.71
Revised Construction Cost:  $2,457,188.73
 
Required Substantial Completion Date:  November 8, 2019
Approved Time Decrease:  53 Calendar Days
Revised Required Substantial Completion Date:  December 31, 2019
Substantial Completion Date:  December 31, 2019

Review Comments

Christopher Farkas , Chief Operating Officer (813) 272-4004