B7.02 - Approve Acceptance of Project for Referendum (Year 1) Project at Burnett Middle School (Operations Division)
The District's referendum advertisement provided for roof and partial heating, ventilating and air conditioning (HVAC) replacements at Burnett Middle School. On February 5, 2019, District staff selected Rowe Architects Incorporated and Batson-Cook Company to provide design and construction management services, respectively, through a selection committee. Award was made based upon the score granted by the selection committee.
The design professional has certified that the work is now fully complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.
N/A
N/A
N/A
* Establish a strong foundation of financial stewardship
* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health
* Construct and maintain facilities that create an environment conducive to teaching and learning
Approve the Acceptance of the referendum project at Burnett Middle School.
Carin Hunt, Project Administrator, carin.hunt@hcps.net, (813) 272-4112
This item is available in the Sales Tax Referendum fund.
Contract Status:
Guaranteed Maximum Price: $7,192,468.00
Approved Change Orders: $2,082,130.70 Credit (See Attachment)
Revised Guaranteed Maximum Price: $5,110,337.30
Payments to Date: $4,815,477.98
Balance Due: $294,859.32
Revised Construction Cost: $6,550,857.33
Required Substantial Completion Date: January 3, 2020
Substantial Completion Date: January 3, 2020