Hillsborough County Public Schools, Florida
Tuesday, 07/28/2020
School Board Meeting
Title

B7.03 - Approve Acceptance of Project for the Referendum (Year 1) Project at Lithia Springs Elementary School (Operations Division)

Description

The District's referendum advertisement provided for heating, ventilating and air conditioning (HVAC), stage equipment replacements and exterior painting  at Lithia Springs Elementary School.  On February 5, 2019, District staff selected SGM Engineering, Inc. and Specialized Property Services, Inc.  to provide design and construction management services, respectively, through a selection committee.  Award was made based upon the score granted by the selection committee.

The design professional has now certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

Gap Analysis

Previous Outcomes

Expected Outcomes

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of the Referendum at Lithia Springs Elementary School. 

Contact

Carin Hunt, Project Administrator, carin.hunt@hcps.net, (813) 272-4112

Financial Impact

This item is available in the Sales Tax Referendum fund.

Contract Status:
Guaranteed Maximum Price: $4,211,230.00
Approved Change Orders:  $603,863.66  Credit (See Attachment)
Revised Guaranteed Maximum Price: $3,607,366.34
Payments to Date:  $3,569,551.44
Balance Due:  $37,814.90
Revised Construction Cost:  $4,081,980.32
 
Required Substantial Completion Date:  August 1, 2019
Approved Time Extension:   148 Calendar Days
Revised Required Substantial Completion Date:  December 27, 2019  
Substantial Completion Date:  December 27, 2019

Review Comments

Christopher Farkas , Chief Operating Officer (813) 272-4004