B7.22 - Approve Acceptance of Project for Temporary Portable Classrooms at McDonald Elementary School (Operations Division)

Description

As part of a recent security assessment, District staff selected Renker, Eich, Parks Architects, Inc. and Batson-Cook Company from the approved Continuing Services Consultants List to provide design and construction management services, respectively.  The scope of work provided for the installation, hook-up and furniture installation of temporary portable classrooms at McDonald Elementary School.

The design professional has now certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

Gap Analysis

Previous Outcomes

Expected Outcomes

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of temporary classroom portables at McDonald Elementary School.

Contact

Carin Hunt, Project Administrator, carin.hunt@hcps.net, (813) 272-4112

Financial Impact

This item is available in the Local Millage fund.

Contract Status:
Guaranteed Maximum Price: $811,714.00
Approved Change Orders:  $117,564.02  Credit (See Attachment)
Revised Guaranteed Maximum Price: $694,149.98
Payments to Date:  $636,798.87
Balance Due:  $57,351.11
Revised Construction Cost:  $694,149.98
 
Required Substantial Completion Date:  August 1, 2019
Substantial Completion Date:  August 1, 2019

Review Comments

Christopher Farkas , Chief Operating Officer (813) 272-4004