B7.12 - Approve Guaranteed Maximum Price (GMP) for Referendum (Year Two) Project at LaVoy Exceptional Center (Operations Division)
On February 5, 2020, District staff selected Engineering Professionals, Inc. and Barr & Barr to provide design and construction management services, respectively, through a selection committee. Award was made based upon the score granted by the selection committee. The project scope provides for a complete heating, ventilating and air conditioning (HVAC) replacement.
Approval of the GMP will establish the cost for the project.
Project Substantial Completion is scheduled for July 23, 2020.
N/A
N/A
Completion of a major mechanical and electrical project resulting in safe, energy-efficient HVAC systems, thereby enhancing the student experience on campus to facilitate learning at LaVoy Exceptional Center.
* Establish a strong foundation of financial stewardship
* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health
* Construct and maintain facilities that create an environment conducive to teaching and learning
Approval of the GMP as prepared by Barr & Barr, representing the design presented by Engineering Professionals, Inc.
Carin Hunt, Project Administrator, carin.hunt@hcps.net, (813) 272-4112
The GMP recommended for approval is $2,205,626, which is available in the Sales Tax Referendum fund.