Hillsborough County Public Schools, Florida
Tuesday, 06/09/2020
School Board Meeting
Title

C7.24 - Approve Acceptance of Project for the Athletic Track at Sligh Middle School (Operations Division)

Description

Sligh Middle School was one of the few middle schools in the district without a running track and sports field.  Operations has corrected this deficiency by providing for the design and construction of a running track and related site work requirements.  District staff selected Key Engineering Associates, Inc. and Skanska USA Building, Inc. from the approved Continuing Services Consultants list to provide design and construction management services, respectively.

The design professional has certified that the work is now fully complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

Gap Analysis

N/A

Previous Outcomes

N/A

Expected Outcomes

N/A

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of the Athletic Track at Sligh Middle School.

Contact

Chuck Plante, Sr. Project Administrator, chuck.plante@hcps.net, (813) 272-4112

Financial Impact

This item is available in the Local Millage fund.

Contract Status:
Guaranteed Maximum Price: $1,665,096.00
Approved Change Orders:  $86,538.80  Credit (See Attachment)
Revised Guaranteed Maximum Price: $1,578,557.20
Payments to Date:  $1,304,469.73
Balance Due:  $274,087.47
Revised Construction Cost:  $1,578,557.20
 
Required Substantial Completion Date:  February 21, 2020
Substantial Completion Date:  February 21, 2020

 

Review Comments

Christopher Farkas , Chief Operating Officer (813) 272-4004