Title

B7.21 - Approve Acceptance of Project for Roof Replacement at Lithia Springs Elementary School (Operations Division)

Description

A previously approved District Facilities Five Year Work Program provided for replacement of the roof at Lithia Springs Elementary School.  District Staff selected Roof Engineering Associates, Inc. from the from the approved Continuing Services Consultants list to provide design services. On June 5, 2019, Board appointed Service Works Commercial Roofing, Inc. to provide construction management services.  The scope of work included removal and replacement of the roof.

The design professional has now certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

Gap Analysis

N/A

Previous Outcomes

N/A

Expected Outcomes

N/A

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of the roof replacement project at Lithia Springs Elementary School.

Contact

Benjamin Moore, Sr. Department Manager, benjamin.moore@hcps.net, (813) 635-1133

Financial Impact

This item is available in the Community Investment Tax fund.

Contract Status:
Contract Sum: $753,760.00
Approved Change Orders:  $141,740.45  Credit (See Attachment)
Revised Contract Sum: $612,019.55
Payments to Date:  $563,218.87
Balance Due:  $48,800.68
Revised Construction Cost:  $782,990.73
 
Required Substantial Completion Date:  November 29, 2018
Approved Time Decrease:  15 Calendar Days
Revised Required Substantial Completion Date:  December 14, 2018
Substantial Completion Date:  December 14, 2018

Review Comments

Christopher Farkas , Chief Operating Officer (813) 272-4004