B7.20 - Approve Acceptance of Project for Security Vestibule at Chamberlain High School (Operations Division)

Description

As part of a recent security assessment, District staff selected Design Styles Architecture, Inc. and J.O. DeLotto & Sons, Inc. from the approved continuing services consultants list to provide design and construction management services, respectively. The scope of work provided for construction of a secured vestibule at Chamberlain High School.

The design professional has now certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.
  

Gap Analysis

N/A

Previous Outcomes

N/A

Expected Outcomes

Provided a secure entrance vestibule to improve safety thereby enhancing the student experience on campus to facilitate learning at Chamberlain High School.

Strategic Plan Goal

* Establish a strong foundation of financial stewardship

* Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health

* Construct and maintain facilities that create an environment conducive to teaching and learning

Recommendation

Approve the Acceptance of the security vestibule project at Chamberlain High School.

Contact

Carin Hunt, Project Administrator, carin.hunt@hcps.net, (813) 272-4112

Financial Impact

This item is available in the Local Millage fund.

Contract Status:
Guaranteed Maximum Price: $870,125.00
Approved Change Orders:  $75,836.38  Credit (See Attachment)
Revised Guaranteed Maximum Price: $794,288.62
Payments to Date:  $4,136.97
Balance Due:  $790,151.65
Revised Construction Cost:  $794,288.62
 
Required Substantial Completion Date:  August 21, 2019
Substantial Completion Date:  August 21, 2019