Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 6, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

VARIOUS SCHOOLS
CLASSROOMS FOR KIDS (PACKAGE 4)
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

On September 7, 2004, the Board appointed John J. McKenna Architect P.A. and Hunt Construction to provide design and construction management services for classroom additions at Cork, Knights and Springhead Elementary Schools. These additions are necessary to meet class size reduction requirements. The scope of work provides for the construction of 16 additional classrooms at Cork, Knights and Springhead Elementary Schools.

Approval of the guaranteed price will provide a maximum cost for the facilities. Completion is scheduled for June 2, 2006.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $6,423,962. The construction budget is 6,423,962. This item is included in the District Capital Outlay: Classrooms for Kids.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.05b
Hillsborough County Public Schools (Florida) * Mtg.#20050906_151 * Section E Item# 6.05b